Friday, 2 October 2009

Week 11 - 25 September 09 to 2 October 09

Bricklayers arrived on site on Tuesday 29th September and started building up lower level of outside walls in brick, until level with floor. I called to see them and made an everlasting first impression by tripping in drive and going A*se over T*t in front of them. However I perfected a perfect parachute roll and was quickly on my feet, slight wrist injury and big pride injury. Quoins arrived on Wednesday and brick layers worked very hard in first week - very impressed with progress, let's hope it continues and fingers crossed for a run of decent building weather.
Progress shown below for this week - see you all next week.